[cssm] [CSSM] SMURF forbidden pass use case
Martin.Unal at esa.int
Martin.Unal at esa.int
Fri Nov 13 15:58:44 UTC 2020
Hello
I believe that if you use the SMURF for constraint based planning, you
have the possibility to provide go/no go time window.
3.11.4 CLASS TimeWindows
The TimeWindows class is optional and may be used to submit a set
of time windows.
Each instance of the TimeWindows class must contain 1 or more
instances of the TimeWindow class described in section 3.11.5.
NOTE ? The TimeWindows class is a specialization of class
Constraints described in 3.10.2 and the generic description of the
parameters can be found there.
The use of the TimeWindows class allows the specification of a set
of one or more time windows that must either all be included or all
excluded in the resulting schedule.
Table 3-37 specifies the use of the parameters in the TimeWindows.
Table 3-37: Class TimeWindows Parameters
Parameter
Description
Data Type
Data Units
includeWindow
If true indicates that the time range specified by the window is
considered to be included.
If false indicates that the time range specified by the window is
considered to be excluded.
xsd:Boolean
n/a
1.1.2 CLASS TimeWindow
Regards
________________________________________
Martin UNAL
Ground Operation Manager
Ground Facilities Ops HSO - ONO
H-376
ESOC
Robert-Bosch Strasse 5
64 293 Darmstadt
Germany
Tel +49 6151 90 2959
________________________________________
From: "Ciocirlan Claudia" <Claudia.Ciocirlan at cnes.fr>
To: "smwg at mailman.ccsds.org" <smwg at mailman.ccsds.org>
Date: 13/11/2020 16:43
Subject: [cssm] [CSSM] SMURF forbidden pass use case
Sent by: "SMWG" <smwg-bounces at mailman.ccsds.org>
Dear all,
Hope you are safe and healthy.
We?ve been discussing with Jean-Michel on the different use cases of the
SMURF and we might have one use case for which we are unable to find a
response.
In our existing tools we have the possibility to mark a pass as forbidden
when requesting for a schedule request. A pass is identified by a station,
a spacecraft, an AOS and a LOS. The ground control center has the
possibility to compute AOS and LOS for the different passes. This way our
planning tool will be able to fulfill all constraints without booking the
forbidden pass. The scenario we managed to make was that the scheduling
tool plans for a list of passes regarding to the constraints and then if
the pass is present, then we need to do a DeleteSrvPkg and then
reschedule again and request for another pass.
Do you have a solution for our use case, a simple one if possible?
Best regards,
Claudia Ciocirlan
Claudia Ciocirlan CNES/DNO/OP/SSO
Mission Operations Ground Segment
phone : +33 (0)5 61 28 17 11
email : claudia.ciocirlan at cnes.fr
P Save a tree ! Think before printing
_______________________________________________
SMWG mailing list
SMWG at mailman.ccsds.org
https://mailman.ccsds.org/cgi-bin/mailman/listinfo/smwg
This message is intended only for the recipient(s) named above. It may contain proprietary information and/or
protected content. Any unauthorised disclosure, use, retention or dissemination is prohibited. If you have received
this e-mail in error, please notify the sender immediately. ESA applies appropriate organisational measures to protect
personal data, in case of data privacy queries, please contact the ESA Data Protection Officer (dpo at esa.int).
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.ccsds.org/pipermail/smwg/attachments/20201113/d3cdbba8/attachment.htm>
More information about the SMWG
mailing list