Dear SEA Exec,

We are being asked by the CMC to do three things:

  1.  Update the area goals (I'll do that)
  2.  Update the current projects and schedules (each WG chair must do that)
  3.  Add new future projects (you must do this as well)

The following message shows what Nestor's assessment is of the specific issues.  Please deal with them this week.

For the future projects my request is that you insert into the Project set any of the projects that you have been discussing in the WG, even if they are still in a very loose, formative, stage.  I know that it is often hard, when you are doing all you can now to get current projects done, to think about future work.  But be aware that the CMC has been asking what this future work looks like.  And they are asking if, when the current projects are done, that the WG will close.  It is certainly possible that that may happen, especially if the work you forecasted is complete.

There is no need to keep a WG going if it has done what it set out to do.  Note that we closed the SEA System Architecture WG (SAWG) when its work on RASDS was completed.  Also note that the CCSDS requirement that standards be reviewed and "refreshed" every five years might mean that WG gets restarted.  We are about to do that with the SAWG to refresh RASDS.

I know that this is added work, but please take an hour of your WG scheduled sessions to brainstorm and describe those future projects that make sense.  Then put them into the framework.

Thanks, Peter


From: Nestor Peccia <Nestor.Peccia at esa.int<mailto:Nestor.Peccia at esa.int>>
Date: Sunday, November 2, 2014 11:42 AM
To: Peter Shames <peter.m.shames at jpl.nasa.gov<mailto:peter.m.shames at jpl.nasa.gov>>, "Weiss, Howard" <Howard.Weiss at parsons.com<mailto:Howard.Weiss at parsons.com>>, Mattia Mercolino <Mattia.Mercolino at esa.int<mailto:Mattia.Mercolino at esa.int>>
Cc: CCSDS Engineering Steering Group - CESG Exec <cesg at mailman.ccsds.org<mailto:cesg at mailman.ccsds.org>>, CMC <cmc at mailman.ccsds.org<mailto:cmc at mailman.ccsds.org>>
Subject: SEA Area: Goals / Project Checks needed in the WGs

Dear all,

As the CESG and CMC will review the current Strategic Plan during our planned joint meeting at London, it is recommended to

  *   check the Area goals and update if needed
  *   check the links wrt published books and update if needed
  *   cross check the schedule of our current books under production and update if needed
  *   include the future work as CWE Projects with a start date (realistic please) in the future

in particular

Security WG

  1.  Network Layer Security Adaptation Profile BB                Completion Date: 18.02.2015                Is Schedule realistic ? If not, include new estimated completion date ?
  2.  Security Threats against Space Mission Revision GB        Completion Date: 01.06.2015                Is Schedule realistic ? If not, include new estimated completion date ?

No more standards foreseen after 2016        /  Q1 2017                                                        Goals achieved ? WG to be disbanded ? or Schedule to be adapted ?

D-DOR WG
No more standards foreseen after 2016        / 2017                                                                Goals achieved ? WG to be disbanded ?

Future Work

  1.  Reference Information Architecture, Infrastructure Services and Interfaces MB                                Insert Project. Start Date in future. Realistic schedule (resources?) to be considered
  2.  XML Standards and Guidelines MB                                                                        Insert Project. Start Date in future.  Realistic schedule  (resources?) to be considered.
  3.  Timeline Data Standard BB                                                                                Insert Project. Start Date in future.  Realistic schedule  (resources?) to be considered.
  4.  Time Service Architecture MB                                                                        Insert Project. Start Date in future.  Realistic schedule (resources?) to be considered.
  5.  CCSDS Standards Reference Architecture MB                                                        Is this a duplication of next book ?
  6.  Reference Architecture for Space Data Systems (Issue 2 after 5 year Review) MB                        Insert Project. Start Date in future.  Realistic schedule   (resources?) to be considered.

ciao
nestor

This message and any attachments are intended for the use of the addressee or addressees only.
The unauthorised disclosure, use, dissemination or copying (either in whole or in part) of its
content is not permitted.
If you received this message in error, please notify the sender and delete it from your system.
Emails can be altered and their integrity cannot be guaranteed by the sender.

Please consider the environment before printing this email.

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.ccsds.org/pipermail/sea-exec/attachments/20141103/015cc995/attachment.html>