Response to MIA questions below next to **
*****
Rodney Grubbs
NASA Imagery Experts Program Manager
MSFC EO50
256-544-4582
256-603-3270 (cellular, text message capable)
Follow me on Twitter @rod4dtv

On Nov 2, 2014, at 12:42 PM, <Nestor.Peccia at esa.int<mailto:Nestor.Peccia at esa.int>>
 wrote:

Dear all,

As the CESG and CMC will review the current Strategic Plan during our planned joint meeting at London, it is recommended to

  *   check the Area goals and update if needed (http://cwe.ccsds.org/fm/sp/default.aspx)
  *   check the links wrt published books and update if needed (http://cwe.ccsds.org/fm/sp/default.aspx)
  *   cross check the schedule of our current books under production and update if needed
  *   include the future work as CWE Projects with a start date (realistic please) in the future

ADs have edit permission to the CWE Strategic Plan (http://cwe.ccsds.org/fm/sp/default.aspx), and they shall check (co-ordinating with the related WG Chair) and update
in particular

MIA WG

  1.  Digital Motion Imagery Applications  BB        Is Schedule realistic ? If not, include new estimated completion date ?

**  Have been discussing this with Keith for some time now.  We have a plan that will get us to completion on time.

No more standards foreseen after 2015                Goals achieved ? WG to be disbanded ? or Schedule to be adapted ?

**  We have a joint meeting with DTN planned for next week to discuss whether to proceed with a bundle streaming service, with video being the killer app.  If the decision is to move forward with that under the DTV WG vs. the MIA WG, then the MIA WG will likely disband.  Bottom line is we'll have schedule and forward plan all sorted out by end of next week.

DTN WG

  1.  BP Network Management  BB                Is Schedule realistic ? If not, include new estimated completion date ?
  2.  Bundle Protocol BB                                Is Schedule realistic ? If not, include new estimated completion date ?
  3.  Bundle Security Protocol BB                        Include realistic start date (resources?)
  4.  Contact Graph Routing (CGR) BB                Include realistic start date (resources?)
  5.  Licklider Transmission Protocol BB                Is Schedule realistic ? If not, include new estimated completion date ?
  6.  Single-Agency NW Management Req GB        Is Schedule realistic ? If not, include new estimated completion date ?

 No more standards foreseen after 2017                Goals achieved ? WG to be disbanded ? or Schedule to be adapted ?

Voice WG

  1.  Voice and Audio Communications  BB        Is Schedule realistic ? If not, include new estimated completion date (resources?)?

 No more standards foreseen after 2016                Goals achieved ? WG to be disbanded ? or Schedule to be adapted ?

CFDP Update WG

  1.  CFDP Update BB                                Is Schedule realistic ? If not, include new estimated completion date (resources?)?
  2.  CFDP Update Implementer's Guide GB        Is Schedule realistic ? If not, include new estimated completion date (resources?)?
  3.  CFDP Update Interoperability Test Plan  GB        Is Schedule realistic ? If not, include new estimated completion date (resources?)?
  4.  CFDP Update Introduction and Overview  GBIs Schedule realistic ? If not, include new estimated completion date (resources?)?

 No more standards foreseen after 2016                Goals achieved ? WG to be disbanded ? or Schedule to be adapted ?

Future Work

  1.  SSI Streaming Service BB                        Include Project in CWE with realistic Start date. Resources ?
  2.  FW for SSI Cross Support and Admin GB        Include Project in CWE with realistic Start date. Resources ?
  3.  Erasure Code for LTP BB                        Include Project in CWE with realistic Start date. Resources ?


ciao
nestor

This message and any attachments are intended for the use of the addressee or addressees only.
The unauthorised disclosure, use, dissemination or copying (either in whole or in part) of its
content is not permitted.
If you received this message in error, please notify the sender and delete it from your system.
Emails can be altered and their integrity cannot be guaranteed by the sender.

Please consider the environment before printing this email.


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.ccsds.org/pipermail/cesg/attachments/20141105/ba3c8fff/attachment.html>


More information about the CESG mailing list