[Tc20-sc13] FW: [CESG] UPCOMING DEADLINE: CCSDS Operating Plan update

debbie.ronning debbie.ronning at btas.com
Sat Mar 26 17:05:25 UTC 2005


FYI

 

  _____  

From: cesg-bounces at mailman.ccsds.org [mailto:cesg-bounces at mailman.ccsds.org]
On Behalf Of Adrian J. Hooke
Sent: Friday, February 11, 2005 11:58 AM
To: CCSDS Engineering Steering Group - ADs
Cc: Gary Forrester
Subject: [CESG] UPCOMING DEADLINE: CCSDS Operating Plan update
Importance: High

 

PLEASE NOTE THE UPCOMING (MONDAY 14 FEBRUARY) DEADLINE TO UPDATE THE CCSDS
OPERATING PLAN. See the attached message for the process. Since Mr. Steve
Harris no longer works for the Secretariat, please have your chairs send
comments to Mr. Gary Forrester <Gary.Forrester at btas.com>

BY 14 FEBRUARY 2004: please ask every one of your WG and BOF chairs to
review their version 3 charter and to submit any requested changes to
reflect current status. In particular, if BOFs have been converted to WGs or
retired, please make the corrections.

I would remind each Area Director that it is your personal responsibility to
ensure the current accuracy of your component of the Operating Plan.

Best regards
Adrian
+++++++




Date: Tue, 01 Feb 2005 14:50:24 -0800
From: "Adrian J. Hooke" <Adrian.J.Hooke at jpl.nasa.gov>
Subject: [CESG] Time to update the CCSDS Operating Plan
List-Post: <mailto:cesg at mailman.ccsds.org>

ADs and DADs: it's time to update the CCSDS Operating Plan and to transmit
the new version to the CMC with a request for a recommitment of Agency
resource allocations.

The version 3 draft that was the baseline for the November 2004 meeting is
attached in PDF format. You can also access the 
Word version of this document in DocuShare at:

http://www.ccsds.org/docu/dscgi/ds.py/View/Collection-666

The process for update is as follows:

1. BY 14 FEBRUARY 2004: please ask every one of your WG chairs to review
their version 3 charter and to submit any requested changes to reflect
current status to Steve Harris, <Stephen.Harris at btas.com> Mr. Gary Forrester
<Gary.Forrester at btas.com>

2. Steve will then prepare a summary of any major changes in scope, schedule
or resources, will edit the document to reflect these changes and will
produce version 4, which he will place back on-line.

3. I will transmit version 4 to the CMC for their review and reconfirmation.
This will become the baseline for the Athens meeting.

CESG members can access previous versions of this plan at:

http://www.ccsds.org/docu/dscgi/ds.py/View/Collection-541

Best regards
Adrian
++++++
6ff3d9.jpg  

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.ccsds.org/pipermail/tc20-sc13/attachments/20050326/57a7f6e6/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: 6ff3d9.jpg
Type: image/jpeg
Size: 216909 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/tc20-sc13/attachments/20050326/57a7f6e6/attachment.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: CCSDS-Op-Plan-v3-Nov2004.pdf
Type: application/pdf
Size: 333513 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/tc20-sc13/attachments/20050326/57a7f6e6/attachment.pdf>
-------------- next part --------------
An embedded and charset-unspecified text was scrubbed...
Name: ATT00018.txt
URL: <http://mailman.ccsds.org/pipermail/tc20-sc13/attachments/20050326/57a7f6e6/attachment.txt>


More information about the TC20-SC13 mailing list