[cssm] DSN Service Agreement Characterization

Barkley, Erik J (US 3970) erik.j.barkley at jpl.nasa.gov
Fri Jan 28 01:36:15 UTC 2022


CSSM Colleagues,

Here is my response on the Service Agreement AI.   Please see the attached file.  I will not be surprised if you find a fair degree of similarity with what Wes has provided, but I think you will also see a few differences.

Any volunteers for taking the 3 inputs (DLR/NSN/DSN) and smashing them into some sort of consistent comparative format? :-)  At a minimum I think we can take a look during the WG telecon next week and make an assessment with regard to having enough information to move ahead with some common set of parameters for the service agreement.

Best regards,
-Erik

From: SMWG <smwg-bounces at mailman.ccsds.org> On Behalf Of Eddy, Wesley M. (GSFC-580.0)[MTI SYSTEMS, INC.] via SMWG
Sent: Wednesday, January 19, 2022 13:47
To: Barkley, Erik J (US 3970) <erik.j.barkley at jpl.nasa.gov>
Cc: CCSDS Service Mgmt WG <smwg at mailman.ccsds.org>
Subject: Re: [cssm] [EXTERNAL] Notes for January 11 telecon + updated action items

For the action on Service Agreement contents, here are generic contents used for some recent NSN service agreement documents.

There are actually 3 different templates, and a Mission Commitment Engineer collaborates with the customer on the services needed, using the appropriate template.

[cid:image001.png at 01D813A4.224F0D40]

I looked at both PSLA and SLA documents for recent missions.  Below is a set of different types of data contained in them.


  1.  Customer Information
     *   Mission Name & Acronym or Short Title
     *   Points of Contact for:

                                                                  i.      The Mission Project's Requirements

                                                                ii.      The Mission Project's Funding

                                                               iii.      The Mission Project's Ground Systems

                                                               iv.      The NSN's Mission Manager assigned

                                                                v.      The NSN's Mission Commitment Engineer

                                                               vi.      The CP (NASA terrestrial network service provider) Customer Service Representative assigned

                                                             vii.      The Flight Dynamics Facility

                                                            viii.      ... any others that might be relevant

     *   Category/Sponsor (checkboxes for the NASA mission directorate or different non-NASA options).
     *   Brief statement of mission objectives.
     *   Launch/Flight Information (indication of launch vehicle, site, operations sites, trajectory regime e.g. injection into LEO, and launch dates)
     *   Orbit/Flight Path Data (checkboxes for high-level options, then orbital parameters)
     *   Key Mission Events and Dates (major review milestones, start of spacecraft I&T, etc.)
     *   Launch and/or Mission-Critical Events (listed)
     *   Formulation and Implementation Phase Start Dates.
     *   Funding information.
     *   Present Phase of Development.
     *   Requirements Maturity Assessment (%)
     *   Potential Services Extension (e.g. L+15 years).
     *   Spacecraft Estimated Lifetime.
     *   Spacecraft Lifetime Limiting Factor.
     *   Stations Requiring Frequency Authorization.
     *   Frequency Authorization Managed by who.
  1.  Customer Requirements and Standard Services
     *   GSFC Networks/Data Services

                                                                  i.      NEN

           *   Service Levels
              *   Launch and Early Orbit Phase

                                                                                     i.      E.g. all available contacts, as many as X per day per specific site.

              *   Spacecraft Activation Phase
              *   Instrument Activation Phase
           *   Service Provided
              *   Tracking
              *   Telemetry
              *   Commanding
              *   Data Formatting and Storage
              *   Scheduling
              *   Testing
              *   Summary Data

                                                                ii.      SN (similar to NEN section, though with slightly different "Services Provided" including Real-time Control and Performance Data Monitoring)

                                                               iii.      Mission Integration and Test

           *   Text and table describing different test types (roughly a dozen, including database, connectivity, data flows, scheduling, end-to-end, etc.), resources, and numbers of tests for each type

                                                               iv.      Radio Frequency Interface Control Document

           *   Reference to separate RFICD document.
     *   DSN Services
     *   Flight Dynamics Facility

                                                                  i.      Initial Acquisition Vectors

                                                                ii.      DOWD Measurements

                                                               iii.      LEOP Acquisition Data

                                                               iv.      Table of FDF Services requested prelaunch, launch & early orbit, on-orbit, contingency, or end-of-mission, including:

           *   Orbit determination
           *   Acq. Data
           *   Manuever planning
           *   Predictive products
           *   Analysis
           *   Tracking data evaluation
           *   Other as requested
     *   Communications Program (CP) - our terrestrial network provider between sites

                                                                  i.      Table of data service requirements between specific sites (e.g. primary MOC, backup MOC, etc. to Goddard or different ground stations, etc).

  1.  Service and Schedule Summary
     *   Funding responsibility
     *   Estimated services for future years (table of different service types per provider needed in upcoming fiscal years)
     *   Customer's Master Schedule
     *   Customer Deliverables (table of technical documents, inputs, reports, etc. and who is providing each by when)
  2.  Networks Integration Documents and Reviews
     *   Checklist of important documents and reviews with hyperlinks
     *   Reference documents






From: SMWG <smwg-bounces at mailman.ccsds.org<mailto:smwg-bounces at mailman.ccsds.org>> On Behalf Of Barkley, Erik J (US 3970) via SMWG
Sent: Wednesday, January 12, 2022 8:33 PM
To: CCSDS Service Mgmt WG <smwg at mailman.ccsds.org<mailto:smwg at mailman.ccsds.org>>
Subject: [EXTERNAL] [cssm] Notes for January 11 telecon + updated action items


CSSM Colleagues,



Attached are the notes from the teleconference on January 11.  Corrections appreciated.    The notes have also been uploaded to the teleconference folder on CWE (meeting materials --> 2022 --> Telecons or  https://cwe.ccsds.org/css/docs/Forms/AllItems.aspx?RootFolder=%2Fcss%2Fdocs%2FCSS%2DSM%2FMeeting%20Materials%2F2022%2FTelecons&FolderCTID=0x012000A2CFA608DF169C4EB988261660CEFAEB&View=%7BD853EDDB%2DF007%2D4BF6%2D8C31%2DBA03A9D0F4A4%7D<https://urldefense.us/v3/__https:/gcc02.safelinks.protection.outlook.com/?url=https*3A*2F*2Fcwe.ccsds.org*2Fcss*2Fdocs*2FForms*2FAllItems.aspx*3FRootFolder*3D*252Fcss*252Fdocs*252FCSS-SM*252FMeeting*2520Materials*252F2022*252FTelecons*26FolderCTID*3D0x012000A2CFA608DF169C4EB988261660CEFAEB*26View*3D*257BD853EDDB-F007-4BF6-8C31-BA03A9D0F4A4*257D&data=04*7C01*7Cwesley.m.eddy*40nasa.gov*7Cfc2f8b9520ad49b4a1e508d9d634ae73*7C7005d45845be48ae8140d43da96dd17b*7C0*7C0*7C637776344750566685*7CUnknown*7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0*3D*7C2000&sdata=w3S1WrRklJvRWcO0f7mM8S9xddXM51qsNnt69HOVvG0*3D&reserved=0__;JSUlJSUlJSUlJSUlJSUlJSUlJSUlJSUlJSUlJSUlJSUlJSU!!PvBDto6Hs4WbVuu7!fTH6AMP386xYsSNg1ppJm35qj9Uo1Q4Dwyg-tq4y9IEaQb5Azd1uu2LSYhhrsoWyFkU4GZ8$> )



Also attached is the updated action item list which has also been posted to the action item folder in the CWE private space.



Our next telecon is scheduled for February 1.



Best regards,

-Erik

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.ccsds.org/pipermail/smwg/attachments/20220128/0b9bd710/attachment-0001.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 38603 bytes
Desc: image001.png
URL: <http://mailman.ccsds.org/pipermail/smwg/attachments/20220128/0b9bd710/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: DSN-SvcAgr-Characterization-220127.pdf
Type: application/pdf