[Moims-rac] Notes from DAI telecon today

John Garrett garrett at his.com
Wed Jan 6 07:04:03 UTC 2016


Hi,

 

Sorry, I thought we decided yesterday not to have meetings this week.

 

I'll take a look at Mark's comments on the ILF version from the CCSDS
meeting.  I also started to add comments to Mike's paper.

 

Wishing you Prosperity and Peace,

-JOhn

 

From: moims-rac-bounces at mailman.ccsds.org
[mailto:moims-rac-bounces at mailman.ccsds.org] On Behalf Of David Giaretta
Sent: Tuesday, January 5, 2016 12:28 PM
To: 'MOIMS-Data Archive Ingestion' <moims-dai at mailman.ccsds.org>;
MOIMS-Repository Audit and Certification Working Group
<moims-rac at mailman.ccsds.org>
Subject: [Moims-rac] Notes from DAI telecon today

 

Dear all

 

Apologies for the lateness of my email about the contact details of the
call. I had not realised that it was held by the CCSDS mailer - I've fixed
things so that this should not happen again.

The call is weekly on Tuesday and the details are:

 

At the time of the call - 3pm UK time - please call

 

UK:        +44 (0) 330 606 0182

USA:      (641) 715-3810

France +33 (0) 7 55 50 04 14

 

For other numbers see
https://www.freeconferencecall.com/free-international-conference-call/intern
ationalphonenumbers.aspx  

 

Participant Access Code:        396476#

 

The conversation was recorded - the first 7 minutes or so are taken up with
setting things up because people had not received the email mentioned above.
If you want to listen to it (about 1 hour):

       

>From the Phone...Dial: +44 (0) 330 606 0719  .  Enter Access Code: 396476#
. The Ref.No. is 1 or just select the latest recording.

Alternatively use link:
https://www.dropbox.com/s/es28rcrs2nhin76/MOIMS-DAI-20160105-recording.mp3?d
l=0 

 

Mike Martin had circulated a concept paper and Mark Conrad had circulated
his mark-up of John Garrett's version of  "Information Lifecycle and Long
Term Usage" (ILCLTU) from mid December.

 

After some discussion is was agreed that in order to try to keep to an
acceptable schedule (i.e. about 10 months' delay to the schedule shown below
- remember that schedule was written almost 3 years ago!) the following
actions are needed:

 

20160105-1:  Due 20160109:  ACTION for ALL send comments on the main
document (ideally Mark's version) 

 

20160105-2:  Due 20160111:  ACTION for DG - circulate a clean version of
ILCLTU integrating all comments and including appropriate pieces from Mike's
paper. If possible a brief mapping to the LTDP workflow will be added in
Annex A, and a draft of Annex C will also be produced.

 

20160105-3:  Due 20160105:  ACTION for DG - circulate schedule from CCSDS
management framework. STATUS: DONE- see below

 

The CCSDS management framework
http://cwe.ccsds.org/fm/Lists/Projects/DispForm.aspx?ID=368
<http://cwe.ccsds.org/fm/Lists/Projects/DispForm.aspx?ID=368&Source=http%3A%
2F%2Fcwe.ccsds.org%2Ffm%2FLists%2FProjects%2FAllItems.aspx&ContentTypeId=0x0
100B63160D64FE81342BE42A874DE7E703D>
&Source=http%3A%2F%2Fcwe.ccsds.org%2Ffm%2FLists%2FProjects%2FAllItems.aspx&C
ontentTypeId=0x0100B63160D64FE81342BE42A874DE7E703D shows the original
schedule for the book "Information Lifecycle and Long Term Usage" (Magenta
Book) which we are working on :


Schedule

	

 


Legend for Schedule Milestones 









 


= Required for Orange Books

= Required for Green Books

= Required for Magenta Books

= Required for Blue Books
(Red Books are Draft Blue/Magenta Books)

Schedule Milestones 

Original Completion Date 
(Date in M/D/YYYY format.)

Estimated Completion Date 
(Date in M/D/YYYY format.)

Actual Completion Date 
(Date in M/D/YYYY format.)

Comments
(Limit 255 Characters)


  Project Approved 









7/31/2013

7/31/2013

4/3/2014

Work on this project should start following completion of PAIS Standard


  Planned Project Start Date  









4/3/2014

4/3/2014

4/3/2014

	

  Internal WG Review 


- First draft circulated to WG 









2/1/2014

6/1/2014

	Some material will be provided by EU LTDP project


- First draft comments due 









4/30/2014

7/1/2014

		

- Second draft circulated to WG 









6/30/2014

9/30/2014

		

- Second draft comments due 









10/31/2014

10/31/2014

		

- Final WB submitted to AD for further processing  









4/30/2015

4/30/2015

		

  Secretariat Document Processing









5/30/2015

5/30/2015

		

  First Agency Review

		



8/30/2015

8/30/2015

		

  RID Resolution

		



10/30/2015

10/30/2015

		

  Secretariat Document Processing

		



11/30/2015

11/30/2015

		

  Final Agency Review

		



2/28/2016

2/28/2016

		

  RID Resolution

		



4/30/2016

4/30/2016

		

  First Prototype Development

			

				

  Second Prototype Development

			

				

  CMC Approval









5/30/2016

5/30/2016

		

Total Time to Complete (in months) 

				25

25

		

 

 

Regards

 

..David

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.ccsds.org/pipermail/moims-rac/attachments/20160106/fc20cc9e/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 2015 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/moims-rac/attachments/20160106/fc20cc9e/attachment.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.jpg
Type: image/jpeg
Size: 2041 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/moims-rac/attachments/20160106/fc20cc9e/attachment-0001.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image003.jpg
Type: image/jpeg
Size: 2418 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/moims-rac/attachments/20160106/fc20cc9e/attachment-0002.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image004.jpg
Type: image/jpeg
Size: 2015 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/moims-rac/attachments/20160106/fc20cc9e/attachment-0003.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image005.jpg
Type: image/jpeg
Size: 833 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/moims-rac/attachments/20160106/fc20cc9e/attachment-0004.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image006.jpg
Type: image/jpeg
Size: 818 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/moims-rac/attachments/20160106/fc20cc9e/attachment-0005.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image007.jpg
Type: image/jpeg
Size: 842 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/moims-rac/attachments/20160106/fc20cc9e/attachment-0006.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image008.jpg
Type: image/jpeg
Size: 834 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/moims-rac/attachments/20160106/fc20cc9e/attachment-0007.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image009.jpg
Type: image/jpeg
Size: 832 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/moims-rac/attachments/20160106/fc20cc9e/attachment-0008.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image010.jpg
Type: image/jpeg
Size: 835 bytes
Desc: not available
URL: <http://mailman.ccsds.org/pipermail/moims-rac/attachments/20160106/fc20cc9e/attachment-0009.jpg>


More information about the Moims-rac mailing list