[Moims-dai] Digital Archive Architecture Design Document Project Plan
John Garrett
garrett at his.com
Fri Dec 9 08:27:59 UTC 2016
Hi,
One more question about the project. Should this be a Green Book
(Informational - not a standard) or a Magenta Book (a Standard, but not a
testable protocol)?
Most of the other CCSDS Architecture documents are Green but some others are
Magenta Books.
I thought we had discussed it just a bit and decided it should be Magenta so
it got reviewed widely. However, the last version of our draft long-term
plan still shows this as a Green Book.
Wishing you prosperity and peace,
-JOhn
From: MOIMS-DAI [mailto:moims-dai-bounces at mailman.ccsds.org] On Behalf Of
John Garrett
Sent: Thursday, December 8, 2016 1:23 AM
To: 'MOIMS-Data Archive Ingestion' <moims-dai at mailman.ccsds.org>
Subject: [Moims-dai] Digital Archive Architecture Design Document Project
Plan
Hi,
I have an Action Item to add a project plan for Digital Archive Architecture
Design Document to CCSDS CWE Framework. I've attached a draft of what I
intend to enter into the CCSDS System before our Tuesday telecon (or I can
try to enter it after if people want to discuss it at the telecon.)
Please feel free to provide any updates you think are appropriate.
>From the overall DAI plan, our plan was to start this project early the
coming year and finish in 2020. I came close but show the project ending in
early 2021. I've created a spreadsheet with estimated times to complete all
the activities throughout the project. I've included the one's required to
show completion dates for in the CCSDS system (the unshaded rows). I've
also added background activities that do not need dates in the CCSDS form,
but they are activities which we need to allot time for and get through.
These are the lightly shaded rows and many of those activities are performed
by CCSDS and are out of our control. I've assigned what I consider as
optimistic times for completion of those tasks. Personally, based on past
experience, I think we may end up behind schedule on those items. I've also
currently included ISO reviews in this document. I planned with the
presumption that we will want to have concurrent CCSDS and ISO reviews. Is
that what others expect for this document? Those activities are shown with
darker shading. Note that the ISO processing takes place in parallel to
the CCSDS review so the time required for the CCSDS review overlaps with ISO
processing and review. Alternatively we could start and end the CCSDS and
ISO reviews at the same time, which we have sometimes done in the past.
Let me know what you think.
Wishing you prosperity and peace,
-JOhn
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.ccsds.org/pipermail/moims-dai/attachments/20161209/31c18797/attachment.html>