[CESG] CMC comments to CCSDS Strategic Plan

Nestor.Peccia at esa.int Nestor.Peccia at esa.int
Mon Jan 6 11:37:48 EST 2014


Happy New Year

REMINDER
------------------

Dear all,

Please find attached the marked-up Strategic Plan with the CMC compiled 
comments.

Schedule is as follows:
AD to deliver  to Nestor its related updated section by end January 2014
Nestor to deliver new version of the first sections of the Plan (Page 1 - 
10) by end Jan 2014
New version of Strategic Plan to CESG for review by mid Feb 2014
Last comments from CESG on 24th Feb 2014
Issue of Strategic Plan Issue 1 to CMC by end February 2014 (1 month prior 
to next CCSDS technical meeting) 

The first file contains all the CMC comments and the second includes the 
comments in the doc.

[attachment "CCSDS Strat Plan Compilation of Comments - Dec 2013.doc" 
deleted by Nestor Peccia/esoc/ESA] [attachment 
"CCSDS-StratPlan-A01x1y1x1-d11v0-5Dec13-CompCmts.docx" deleted by Nestor 
Peccia/esoc/ESA] 

In addition, Juan Miro has prepared a presentation (attached below)
[attachment "CCSDS Strategic Roadmap 131210 rev1.pptx" deleted by Nestor 
Peccia/esoc/ESA] 

with comments per area, shown below and for your consideration. One of the 
main point of discussion at CMC was:
AD to state either that the Area has no long term objectives (2018-2020+) 
and once the work is completed the Area will be closed. or to include the 
missing long term objectives in the Plan

SEA
SEA plan of work does not seem to contain approved documents (documents in 
CWE but number missing)
SEA midterm focus is timeline exchange 
SEA long term plan is to standardise time services; this was discussed a 
long time ago in CMC but not approved; is it still a valid prospect?

MOIMS
MOIMS Goal 1 ?Spacecraft Conjunction Data Exchange? and Goal 5 ?Digital 
Repository Criteria? have no on-going nor future work planned
Mid-term objectives (2017-2018) only for MO services 
No long terms objectives (2019-2010) defined
Workplan for Tele-robotics is yet to be defined

CSS
Service Management goals defined in the long term, but no approved 
documents
Generic File Transfer is missing from the Strategic Plan although a BoF 
has been established and concept paper is being elaborated

SOIS
Only short term (2014-2015) workplan defined

SLS
RF&M: short and mid-term plan are defined
Coding schemes and synchronisation short, mid and long-term plans 
identified
Space Data Link protocols workplan to be elaborated between 204 and 2018
Data compression and Space Data link security workplans only cover the 
short term
Optical comms workplan is the only goal covering the long term 

SIS
SIS Goal 1 ?Use of Internet standards? has no associated workplan
No goal covers the long term (beyond 2017

ciao
nestor
This message and any attachments are intended for the use of the addressee or addressees only.
The unauthorised disclosure, use, dissemination or copying (either in whole or in part) of its
content is not permitted.
If you received this message in error, please notify the sender and delete it from your system.
Emails can be altered and their integrity cannot be guaranteed by the sender.

Please consider the environment before printing this email.

-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.ccsds.org/pipermail/cesg/attachments/20140106/c85df667/attachment.html


More information about the CESG mailing list