[CESG] Fw: CMC Provisions on CSSM projects
Nestor.Peccia at esa.int
Nestor.Peccia at esa.int
Tue Dec 3 03:58:01 EST 2013
Peter and Martin
Please let us know if your conditions are satisfied, such that the
Projects can be finally approved and made active in CWE / ICPA
ciao
nestor
----- Forwarded by Nestor Peccia/esoc/ESA on 03/12/2013 09:51 -----
From:
"Barkley, Erik J (3970)" <erik.j.barkley at jpl.nasa.gov>
To:
"Martin.Pilgram at dlr.de" <Martin.Pilgram at dlr.de>, "peter.allan at stfc.ac.uk"
<peter.allan at stfc.ac.uk>,
Cc:
Mike Kearney <Mike.Kearney at nasa.gov>, "Nestor.Peccia at esa.int"
<Nestor.Peccia at esa.int>, "Tai, Wallace S (9000)"
<wallace.s.tai at jpl.nasa.gov>, "Margherita.di.Giulio at esa.int"
<Margherita.di.Giulio at esa.int>, "Colin.Haddow at esa.int"
<Colin.Haddow at esa.int>, "Shames, Peter M (312G)"
<peter.m.shames at jpl.nasa.gov>
Date:
03/12/2013 04:01
Subject:
CMC Provisions on CSSM projects
Martin and Peter, I note the following provisions from the CMC polls on
the CSSM projects:
>From Martin: ?please update the dates for the green book, estimated dates
have already past by.
please update the dates for the blue book, estimated dates have already
past by. If there are more than two drafts, include the dates for the
firtst two and then the final white book date.
The working group indicated in the framework a lot of other projects which
are "agreed" on (11.11.2013), which are not listed here, because they
start later on. If the projects should be agreed on then CMC should vote
as well on these projets today.:
>From Peter: ?I agree with Martin's comments about needing to update
information. I also note that the implication of the information in the
CWE is that considerable work has taken place before the project came to
the CMC for approval.?
My comments:
1) Yes, Peter is correct in that work has been done prior to the
request for CMC approval. This is, to some extent, a function of having
adopted the revised approach at the Bordeaux meetings (which I included in
my briefing to the CMC this past April). Prior to the approach adopted in
Bordeaux a somewhat different approach was being pursued and the original
project definitions had those dates but I was not confident until after
the Bordeaux meetings and revised approach that the green book and
schedule of services blue books projects would progress properly with the
resources available. There are still future dates listed on these
projects, and those are indeed correct and reflective of the current
estimates as to delivery (i.e. the WG expects the green book to be going
to CESG review in early 2014, the schedule book to be available for agency
review by May 2014). I have updated some of the dates where it makes
sense to do so. Nonetheless there are some dates still in the past that
reflect the actual work done at that time. I trust that the updated dates
(where appropriate) satisfy the provision.
2) Yes, Martin is correct that there are several other projects that
are to be eventually initiated, worked. In good conscious, I cannot claim
to have the resources available such that these projects will complete at
their estimated dates, let alone start at the current estimated dates. The
start date for these all tend to be quite a ways out -- literally years
from now. As such, the resource picture will likely change. My
preference is to get the projects for which we have resources completed
and subsequently produce a more accurate estimate as to when the further
future projects will be completed and request their initiation (given the
resource profile at that time.) In this manner you do not have to review
reports about projects that are making no progress etc. If the CMC
insists I can indeed make these available for vote but I prefer not to
entertain questions as to why these projects are not advancing when they
are in fact not scheduled to start for quite some time. I believe that
only having those projects on the books for which we currently have
adequate resources will help to keep both the working group and CMC
focused on those truly active projects. Also, it is possible that there
will be changes in the CCSDS technical landscape requiring project
re-definition/re-evaluation. The information will remain in the framework
for reference. Please let me know if this approach is adequate or if
indeed all projects should be voted on even though some do not start until
the 2018 timeframe.
Best regards,
-Erik
Erik Barkley
Cross Support Services Area Director
Consultative Committee for Space Data Systems
erik.barkley at jpl.nasa.gov
+1 818.393.4972
This message and any attachments are intended for the use of the addressee or addressees only. The unauthorised disclosure, use, dissemination or copying (either in whole or in part) of its content is not permitted. If you received this message in error, please notify the sender and delete it from your system. Emails can be altered and their integrity cannot be guaranteed by the sender.
Please consider the environment before printing this email.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.ccsds.org/pipermail/cesg/attachments/20131203/7835afae/attachment-0001.htm
More information about the CESG
mailing list